Salerno · Project Control Quality Manual · SAL-QM-01 Rev. 1 ← Website
Document SAL-QM-01 · Revision 1 · 2026 · Controlled Copy

Salerno Consultancy Company WLL

Project Control
Quality Manual

How Salerno plans, controls and reports every project — our methodology, the nD framework, schedule architecture, control areas, reporting system, Academy and standards, in one controlled reference.

Issued bySalerno Consultancy Company WLL — Manama, Bahrain
ScopeProject control services on EPC and industrial projects
Document ownerCEO / Project Controls Manager
Revision1 — aligned to the published methodology, 2026
Companion sitesalernocompany.com — Method, Reports, Academy
StatusControlled copy — uncontrolled when printed
Salerno Consultancy Company WLLSAL-QM-01 · Rev. 1Page 1

Contents

Table of Contents

01Purpose & Scope
02Quality Policy
03Organisation & Responsibilities
04The nD Project Control Framework (3D → 7D)
05Delivery Methodology — the Control Cycle & Nine Phases
06Schedule Architecture — the Four Levels
07Project Control Processes (EVM · AWP/4D · Cost · Risk)
08The Eight Control Areas
09Reporting System & Key Performance Indicators
10Reference Reports Catalogue
11Document & Change Management
12Tools & Standards
13Competence & the Salerno Academy
14Continuous Improvement
15Track Record & Evidence
16Document Control & Approval
Salerno Consultancy Company WLLSAL-QM-01 · Rev. 1Page 2
01

Purpose & Scope

This manual defines the quality system Salerno applies to its project control services. It describes how we plan, measure, control and report time, cost and performance on EPC, oil & gas, nuclear, power, chemical, data-center and industrial projects.

It applies to all Salerno engagements and personnel, and to the partners and associates who deliver work under the Salerno name. Its purpose is to ensure that every project is controlled consistently, transparently and to the same standard, regardless of sector or location. The manual is the controlled counterpart of the methodology published on salernocompany.com.

02

Quality Policy

Quality, for Salerno, is the discipline of measuring what was planned, what was done, and what it actually cost — and acting early on the difference.

"Process + Technologies + Resources = Culture."
— Marcelo Robles, CEO

Our quality policy rests on five commitments:

03

Organisation & Responsibilities

Salerno operates as a focused team of project control specialists supported by an official partner network. Core roles and responsibilities:

RoleResponsibility
CEO / PC ManagerQuality policy ownership, client assurance, methodology authority
Interface ManagerStakeholder coordination, document & communication interface
Planner / SchedulerBaseline, schedule maintenance, critical-path & progress
Cost ControllerBudget, commitments, earned value, forecast (EAC / VAC)
Partner NetworkSpecialist engineering, software and regional delivery
Salerno Consultancy Company WLLSAL-QM-01 · Rev. 1Page 3
04

The nD Project Control Framework

A model doesn't stop at three dimensions. Salerno extends the digital project from geometry to the full life cycle — each added dimension a new layer of control, from constructability through operation. This nD framework, our Digital Management approach, is the spine of every engagement.

DimensionControl layerWhat it adds
3DConstructabilityPre-construction modelling, clash detection and a build that is right before it starts.
4DTime PlanningThe 3D model joined to the schedule — Critical Path Method, sequencing and simulation.
5DCost & RiskCost management plus risk & opportunities, connected live to time and progress.
6DSustainabilityEnergy, environmental and whole-life performance built into the model.
7DOperation & MaintenanceThe digital twin handed to the owner for asset and facility management.

Reference · method.html — Digital Management nD

Heritage — 4D before it had a name

The Salerno method traces back more than two decades. As early as 2004 we linked Primavera schedules to 3D models to simulate construction sequence week by week — building Digital Twins before the industry had named them. This continuity, from 2004 simulations to today's nD practice, is what gives the method its depth.

Salerno Consultancy Company WLLSAL-QM-01 · Rev. 1Page 4
05

Delivery Methodology

Every project is controlled through one integrated cycle — from an empty site to a project closed on time and on cost.

Phase 01
Define
Objectives, budget and milestones agreed as the baseline.
Phase 02
Plan
Scope, WBS, work packages, resources, schedule baseline.
Phase 03
Monitor
Progress, earned value and cost against baseline.
Phase 04
Control
Variances, forecast and early corrective action.

The Know-how Control Cycle

Within that cycle, control runs continuously through three repeating stages:

01Planning
Management StructuresPBS · OBS · ABS · WBS
OrganizationRoles, responsibility, interfaces
Time ScheduleCritical Path Method (CPM)
02Monitoring
Data CollectionWork progress & manhours spent
Update ActualProgressing the live schedule
Earned ValueBCWS · ACWP · BCWP
03Control
Schedule AnalysisVariances & slipping indexes
Impact AssessmentEffect on project goals
Reporting LevelStrategic · Management · Operative

Nine Disciplined Phases

On engineering & construction programmes, the cycle is delivered through nine phases:

Salerno Consultancy Company WLLSAL-QM-01 · Rev. 1Page 5
06

Schedule Architecture — the Four Levels

One project, four resolutions. Salerno structures every programme from the contractual master schedule down to the three-week look-ahead, so every stakeholder reads the right level of detail for their decision.

LevelScheduleContentView
L1Master SchedulesProject Master Schedule · "S" curve · overall master histogram.Executive
L2Project Level Schedules90-day front-end schedule · critical-path network for the project.Management
L3Detail Level SchedulesEngineering issue, procurement & contracting, plus CPM networks for construction, pre-commissioning and commissioning.Control
L4Control Level Schedule3-week look-ahead work schedules — the short-interval plan that drives the field.Execution

Reference · method.html — Schedule Levels

Each level rolls up into the one above it: the look-ahead feeds the detail schedules, which feed the project schedule, which feeds the master. A single change in the field is therefore visible — correctly summarised — all the way to the executive S-curve.

Salerno Consultancy Company WLLSAL-QM-01 · Rev. 1Page 6
07

Project Control Processes

Earned Value Management (EVM)

Performance is measured by integrating schedule, cost and scope: BCWS (planned value), ACWP (actual cost) and BCWP (earned value), from which SV, CV, SPI, CPI and Estimate At Completion (EAC) are derived.

Advanced Work Packaging (AWP) & 4D

Work is structured into construction work packages (CWP / IWP) aligned to the schedule; combined with the 3D model it produces a 4D Digital Twin for simulation, field coordination and constraint removal.

Cost Control & Risk

Budgets, commitments and forecasts are controlled against the baseline; risks are logged, assessed and mitigated, with EVM-based early-warning indicators driving corrective action while there is still time to act.

08

The Eight Control Areas

We don't just track the schedule — we control the whole project. Every engagement is organised into eight integrated control areas, the structure that has underpinned our reporting since 2002.

01Cost & Progress
02Baseline Estimate
03Schedule Interface
04Engineering Progress
05Document Control
06Capital Equipment
07Procurement
08Material Management

Reference · method.html — Eight Control Areas

Salerno Consultancy Company WLLSAL-QM-01 · Rev. 1Page 7
09

Reporting System & KPIs

Reporting turns data into decisions. Standard deliverables include baseline-vs-current schedules, critical-path analysis, S-curves, manpower histograms, progress certificates and an integrated control dashboard.

IndicatorFormulaMeaning
SPIBCWP / BCWSSchedule efficiency
CPIBCWP / ACWPCost efficiency
SVBCWP − BCWSSchedule variance
CVBCWP − ACWPCost variance
EACBAC / CPIEstimate at completion
VACBAC − EACVariance at completion
10

Reference Reports Catalogue

Each control area produces a defined set of controlled reports. The catalogue below is the standard reporting package; live samples are published on the website.

AreaReports
01 · Cost & ProgressCost Graphs · Cost Reports · Cost Specials
02 · Baseline EstimateEstimate Reports
03 · Schedule InterfaceSchedule Reports
04 · Engineering ProgressEngineering Reports
05 · Document ControlDocument Reports
06 · Capital EquipmentEquipment Reports
07 · ProcurementContract Reports · PO Reports
08 · Material ManagementMaterial Reports

Reference · sample-reports.html — downloadable report catalogue

Salerno Consultancy Company WLLSAL-QM-01 · Rev. 1Page 8
11

Document & Change Management

All project documents are uniquely numbered, revision-controlled and issued through transmittals. Changes are managed through a structured process — Field Design Instruction (FDI), Change Notice (CN) and Variation / Site Scope (VSS) — so every change to scope, schedule or cost is recorded, assessed and approved.

12

Tools & Standards

Salerno works with industry-standard platforms, applied consistently across projects:

Personnel competence on these platforms is maintained through recognised certifications: Saudi Aramco K3, AWP Professional, Primavera P6 Advanced, and Synchro 4D.

Salerno Consultancy Company WLLSAL-QM-01 · Rev. 1Page 9
13

Competence & the Salerno Academy

Competence is maintained and grown through the Salerno Academy — a structured curriculum that transmits 25+ years of EPC project-control judgement, taught on real project data. Nine courses, one discipline:

CodeCourseLevel
EVM-01Earned Value Management MasterclassAdvanced
P6-02Primavera P6, Planning & SchedulingFoundation+
AWP-03Advanced Work Packaging & 4D Digital TwinExpert
COST-04Cost Control & ForecastingCore
RISK-05Project Risk ManagementCore
PC-06Project Controls FundamentalsFoundation
ND-07Digital Project Control — nD MethodologyAdvanced
BIM-08BIM for Project ControlExpert
DC-09Data Center & Mission-Critical ControlsCore

Reference · training.html — Salerno Academy

14

Continuous Improvement

Lessons learned from each project are captured and fed back into the method. Variances, recoveries and judgement calls become Academy material; the Academy, in turn, raises the baseline standard of the next engagement. The method is therefore never static — it compounds.

Salerno Consultancy Company WLLSAL-QM-01 · Rev. 1Page 10
15

Track Record & Evidence

The methodology in this manual is not theoretical. It is the same system applied across more than two decades of major capital projects.

25+
Years expertise
22+
Major projects
7
Industries
4
Continents
EvidenceDetail
Client approvalSaudi Aramco K3 approved project-control capability
SectorsOil & gas · nuclear · power · chemical · data-center · industrial · infrastructure
Heritage4D Digital Twin simulations since 2004; control system since 2002
FootprintBased in Manama, Bahrain & Sweden — delivering globally

Reference · projects.html · case-studies.html · dashboard.html

Salerno Consultancy Company WLLSAL-QM-01 · Rev. 1Page 11
16

Document Control & Approval

This manual is a controlled document. It is reviewed at least annually and whenever the methodology materially changes. Printed copies are uncontrolled.

Rev.DateDescriptionPrepared
02026First issueSalerno PC
12026Aligned to published methodology — added nD framework, schedule levels, eight control areas, reports catalogue, Academy curriculum and track record.Salerno PC

Approval

This Quality Manual is approved for use by:

Prepared by
Name · Role · Date
Approved by — CEO
Marcelo Robles · CEO · Date
Salerno Consultancy Company WLLSAL-QM-01 · Rev. 1Page 12