Prepare the Budget
Open the project from the contract and proposal estimate (ONS). Build the operative budget keeping the project margin unchanged, and schedule costs, revenues and invoicing — the Project Revenue Schedule (PRS).
Procedure · Live Project Data
A disciplined monthly procedure that links forecast-to-complete with the accounting system — turning raw site and invoice data into a reliable, real-time view of cost, revenue and margin. Proven on real EPC programmes.
The Procedure
From the opening of the project to the monthly cost report — a closed loop that keeps the project margin visible at every step.
Open the project from the contract and proposal estimate (ONS). Build the operative budget keeping the project margin unchanged, and schedule costs, revenues and invoicing — the Project Revenue Schedule (PRS).
Each month, collect actual man-hours, physical progress, materials and invoices. Update engineering, material and construction costs, and active billing — actual vs budget, month by month.
Compute committed costs (issued orders, spent man-hours) and the estimate-to-complete. Expected total cost = commitment + estimate-to-complete — the forecast that drives decisions.
Issue cost control reports with summary charts and indicators: gross profit, margin percentage and work-in-progress (WIP). Revenues, costs, margin and invoicing — at a glance.
The Monthly Cycle
A cycle well organised allows a cost control report updated in real time, with a reliable forecast for the following month.
Internal/external man-hours (ADM/PM), updated engineering plan, quantities and direct man-hours (CM), procurement orders & deliveries.
Update costs of direct and indirect resources, physical progress, equivalent construction progress and efficiency / efficacy analysis.
Administration sends the provisional economic situation, recorded and analysed by Cost Control with the PM — actions agreed before release.
A cost control report updated in real time, with a reliable forecast for the following month and early warning on margin.
The Engine · Cost Equations
Cost control is not opinion — it is arithmetic applied with discipline. These are the equations behind every Salerno cost report.
Engineering = accounting man-hours × updated rate · Materials = invoices received · Construction = work-progress income (monthly).
Engineering & commissioning = spent man-hours × updated rate · Materials = updated cost of issued orders · Subcontract = % physical progress × total subcontract (monthly & accumulated).
Estimate-to-complete = orders to be issued · Total expected = commitment + to-be-committed · Expected total cost = commitment + estimate-to-complete.
Elements & Indicators for Cost Control
Live Project Data · Hydroelectric Plant · 2003
A real cost control engagement on a hydroelectric plant programme. The man-hours S-curve tells the whole story at a glance: planned (budget), spent (actual), value delivered (earned) and the projection to completion (forecast) — time now, 30 April. In earned-value terms: Budget = BCWS, Actual = ACWP, Earned = BCWP — the same indices that drive SPI and CPI.
The reading a project manager wants: behind plan (SPI 0.62) but cost-efficient (CPI 1.10) — more value earned per hour than planned. The forecast recovers to budget by June, and every figure reconciles back to the accounting system, not a spreadsheet in isolation.
Live Project Data · Residential Complex · 2004
The same procedure on a residential complex — the project Salerno also modelled in 4D. Cost control reconciled revenue, cost and gross margin month by month, holding the project margin steady to handover.
Illustrative figures · residential complex cost control
Live Project Data · Cash Flow
Cost control doesn't stop at margin — it projects the cash. Cumulative curves for revenue, cost, receipts (cash in) and disbursements (cash out) reveal the financing need across the whole project life, with 90-day payment terms.
The gap between receipts and disbursements is the cash the project must finance. Knowing it months ahead is the difference between a funded project and a stalled one — and it ties directly to WIP (revenue − invoiced).