Procedure · Live Project Data

Cost Control,
Margin Under Control

A disciplined monthly procedure that links forecast-to-complete with the accounting system — turning raw site and invoice data into a reliable, real-time view of cost, revenue and margin. Proven on real EPC programmes.

The Procedure

Four Stages,
One Cycle

From the opening of the project to the monthly cost report — a closed loop that keeps the project margin visible at every step.

01

Prepare the Budget

Open the project from the contract and proposal estimate (ONS). Build the operative budget keeping the project margin unchanged, and schedule costs, revenues and invoicing — the Project Revenue Schedule (PRS).

ONSOperative BudgetPRS
02

Actualize Costs

Each month, collect actual man-hours, physical progress, materials and invoices. Update engineering, material and construction costs, and active billing — actual vs budget, month by month.

Man-hoursInvoicesProgress
03

Commitment & Forecast

Compute committed costs (issued orders, spent man-hours) and the estimate-to-complete. Expected total cost = commitment + estimate-to-complete — the forecast that drives decisions.

CommitmentETCForecast
04

Reporting & Indicators

Issue cost control reports with summary charts and indicators: gross profit, margin percentage and work-in-progress (WIP). Revenues, costs, margin and invoicing — at a glance.

Gross ProfitMargin %WIP

The Monthly Cycle

A Rhythm That
Never Slips

A cycle well organised allows a cost control report updated in real time, with a reliable forecast for the following month.

Day 7
Collect Inputs

Internal/external man-hours (ADM/PM), updated engineering plan, quantities and direct man-hours (CM), procurement orders & deliveries.

Analyse
Update & Reconcile

Update costs of direct and indirect resources, physical progress, equivalent construction progress and efficiency / efficacy analysis.

Day 15
Economic Situation

Administration sends the provisional economic situation, recorded and analysed by Cost Control with the PM — actions agreed before release.

Real Time
Issue Report

A cost control report updated in real time, with a reliable forecast for the following month and early warning on margin.

The Engine · Cost Equations

Every Number
Has a Formula

Cost control is not opinion — it is arithmetic applied with discipline. These are the equations behind every Salerno cost report.

ACT
Actual Cost

Engineering = accounting man-hours × updated rate · Materials = invoices received · Construction = work-progress income (monthly).

CMT
Commitment Cost

Engineering & commissioning = spent man-hours × updated rate · Materials = updated cost of issued orders · Subcontract = % physical progress × total subcontract (monthly & accumulated).

FCT
Forecast Cost

Estimate-to-complete = orders to be issued · Total expected = commitment + to-be-committed · Expected total cost = commitment + estimate-to-complete.

Elements & Indicators for Cost Control

Revenue
= (cost accumulated to date ÷ estimated total cost)
  × estimated total revenue
Gross Profit monthly & accumulated
Actual = revenues to date − costs to date
Estimated = estimated revenues − estimated costs
Margin %
Actual = (accum. revenue − accum. cost) ÷ accum. revenue
Estimated = (total rev. − total cost) ÷ total revenue
WIP — Work In Progress
= revenue − invoiced
Positive when invoiced is less than already expended

Live Project Data · Hydroelectric Plant · 2003

Budget · Actual · Forecast
· Earned

A real cost control engagement on a hydroelectric plant programme. The man-hours S-curve tells the whole story at a glance: planned (budget), spent (actual), value delivered (earned) and the projection to completion (forecast) — time now, 30 April. In earned-value terms: Budget = BCWS, Actual = ACWP, Earned = BCWP — the same indices that drive SPI and CPI.

Man-hours · Budget / Actual / Forecast / Earned TIME NOW · 30 APRIL 1000 2000 3000 4000 5000 6000 0 DECJANFEBMARAPRMAYJUN BUDGET ACTUAL FORECAST EARNED
6,400
Budget Man-hours (BAC)
3,600
Actual · ACWP @ 30 Apr
0.62
SPI · Schedule Index
1.10
CPI · Cost Index

The reading a project manager wants: behind plan (SPI 0.62) but cost-efficient (CPI 1.10) — more value earned per hour than planned. The forecast recovers to budget by June, and every figure reconciles back to the accounting system, not a spreadsheet in isolation.

Live Project Data · Residential Complex · 2004

The Bottom Line
Is the Margin

The same procedure on a residential complex — the project Salerno also modelled in 4D. Cost control reconciled revenue, cost and gross margin month by month, holding the project margin steady to handover.

See the reporting system

Economic Summary · Update 01 Sep
Revenue
3,300,000
Cost
2,800,094
Gross Margin (M.L.)
499,906
Margin %
15.15%

Illustrative figures · residential complex cost control

Live Project Data · Cash Flow

Revenue, Cost &
the Cash Position

Cost control doesn't stop at margin — it projects the cash. Cumulative curves for revenue, cost, receipts (cash in) and disbursements (cash out) reveal the financing need across the whole project life, with 90-day payment terms.

Cumulative Cash Flow · €000 RESIDENTIAL COMPLEX · 90-DAY TERMS 500 1.000 1.500 2.000 2.500 3.000 0 Q1Q2Q3Q4Q5Q6Q7Q8Q9 REVENUE COST RECEIPTS (CASH IN) DISBURSEMENTS

The gap between receipts and disbursements is the cash the project must finance. Knowing it months ahead is the difference between a funded project and a stalled one — and it ties directly to WIP (revenue − invoiced).

Bring Your Margin
Under Control.

Talk to Salerno →